Seismic shifts: 10 years of learning

Click to enlarge
The Auckland Airport international terminal utilised the flange bolted joint – one of two forms of semi-rigid beam to column connections developed by Dr Charles Clifton during his PhD research.

The Auckland Airport international terminal utilised the flange bolted joint – one of two forms of semi-rigid beam to column connections developed by Dr Charles Clifton during his PhD research. Image: Supplied by D&H Steel Construction Ltd

1 of 2
The other of the joints developed by Clifton is the sliding hinge joint, which is more appropriate for higher seismic zones, like Wellington, where it was used in Te Puni Village, seen here.

The other of the joints developed by Clifton is the sliding hinge joint, which is more appropriate for higher seismic zones, like Wellington, where it was used in Te Puni Village, seen here. Image: Supplied by D&H Steel Construction Ltd

2 of 2

Dr Charles Clifton, Associate Professor of Civil Engineering at the University of Auckland, explores what 10 years of engineering research after the Christchurch earthquakes has taught us about building resilient structures.

The 10 years since the most destructive of the Canterbury earthquake series have been filled with work. In my case, some of that has included being part of a working group that has analysed why certain structures (such as the CTV building) failed and what goes into making buildings more resilient under severe seismic stress.

In collaboration with HERA (New Zealand’s Heavy Engineering Research Association), the University of Canterbury Associate Professor Gregory MacRae and Auckland University of Technology Senior Lecturer Shahab Ramhormozian, we’ve worked towards resolving the challenges around building performance, human safety and the cost of construction and remedial strengthening in light of what we learned from Christchurch, for the safety and benefit of all New Zealanders.

Where, then, has a decade of analysis and rebuilding brought us to? Here is what we’ve found:

Our steel buildings performed astonishingly well. In fact, analysis after the February 2011 earthquake showed the Christchurch buildings with standard construction of concrete floors on steel decks supported on steel beams were about 2.5x more resilient than industry-led design had calculated. These buildings use the ‘strong column, weak beam’ design model which allows steel structures to be ductile and move under severe seismic loading while being rigid under wind or moderate earthquakes.

Conversely, the CTV building failed, collapsing pancake-like, because earlier remedial strengthening work (done around two years after it was first built, based on an engineering inspection that identified critical weakness), only addressed the connection between the shear core and the top three floors, leaving the bottom three floors vulnerable to seismic forces. We know this because a survivor testified that when the earthquake started, her third-level floor fell from underneath her, indicating that the lower floors failed first. However, that was only the final catastrophic stage of a building with significant deficiencies right from the initial design.

Steel structure resilience was also demonstrated in HERA’s commissioned research on the performance of structural steel buildings post the Kaikoura Earthquake. Structural steel buildings in the region performed very well during the earthquake, overall, showing that there were no deficiencies in New Zealand’s seismic design practice for steel building structures at that time.

Modern buildings are designed for “controlled damage”. If we think of buildings like a car, in the worst-case scenario like a head-on collision at high speed, we want the car to take the brunt of the force and the people inside it to survive unscathed – then we figure out whether the car can be repaired or must be replaced. Our seismic design procedures for multi-storey buildings have been based on this controlled damage model which allows the building, in the event it is overloaded by seismic activity, to stay standing while people evacuate, then the damage is assessed. This is how steel structures that went through the Christchurch earthquakes were designed to behave and they did that very well, generally with minimal structural and non-structural damage despite the very high severity of the earthquake.

Increasingly, more and more clients – people funding multi-storey construction – want the building to be fully functional after a severe event, so it is not uninhabitable for a long time and any repair work is unnecessary or can be done quickly and safely. With steel structures and composite floors, we are well down the track towards making this a reality, partly because steel structures performed so well in the earthquakes; we can build on that to make them “no-damage” at the design level.

This resilience doesn’t need to cost more. Advancing the strong-column-weak-beam model to a no-damage model has historically been a question of how you design economically for a low-probability event, as earthquake previously was in the Canterbury region. Now, we have a case study that shows the cost of designing for no-damage adds only 1-2 per cent to the structure cost, meaning less than 1 per cent on the overall building cost. This largely eliminates concerns about extra cost to enhance safety and performance.

There is room for improving the efficiency of steel construction. In-situ concrete, where concrete is poured around a steel framework, is highly earthquake-resilient; pre-cast concrete is not. However, use of pre-cast in low seismic zones, such as Auckland (where construction is 50:50 concrete and steel) is appropriate. The focus should be on designing to the conditions and risks, and New Zealand is doing that well; for instance, precast floors are not being used in high-seismic regions. Steel’s ability to accommodate different building shapes and design makes it highly versatile. However, we can still find more efficiencies in how we use it in construction.

Quality control remains paramount. HERA has done a lot of work over the past few years to make certain that all steel coming into New Zealand, whether fabricated (to go straight into buildings) or pieces of steel for local fabrication, complies with the same level of quality that we require of local producers. This has come in the form of their guide to imported steel work, and in-depth seismic research in areas such as welded connections, brittle fracture, and seismic resisting systems delivered via Fabrication 4.0 General Manager Michail Karpenko.

We have seen a few examples such as a hotel at Christchurch airport where the building programme was not met because of quality of construction. We have the procedures and the knowledge in place to prevent that from happening in the future.

In New Zealand multi-storey construction, it’s up to the design team to put an inspection plan in place and designate the inspectors, and the building consent authorities are typically completely hands-off. If the parties involved at that stage are knowledgeable and act with integrity, you get an extremely good solution for very low compliance costs.

The problem – and this is a risk for the regulatory bodies and industry, led by government, to mitigate – is if any one of those parties lacks knowledge or integrity, you can get a poor performing solution which at worst can be disastrous, such as the CTV building.

The current building consent and control system works well only when everyone knows what they’re doing and is interested in doing a good job.


More practice