The final push: SGA and A+W•NZ Motu Kaikoura workshop

Click to enlarge
The team at the end of Day 1 of assembly on the completed floor platform.

The team at the end of Day 1 of assembly on the completed floor platform.

1 of 20
High pressure to unpack the pre-cut deck joists from the flat-packed floor cartridges between helicopter drops.

High pressure to unpack the pre-cut deck joists from the flat-packed floor cartridges between helicopter drops.

2 of 20
Anna Boow completing the southern viewing deck.

Anna Boow completing the southern viewing deck.

3 of 20
The team unpacking the flat packed drops of building components between helicopters drops and securing wall panels in place.

The team unpacking the flat packed drops of building components between helicopters drops and securing wall panels in place.

4 of 20
Flat-packed wall panels are lifted and stood in place for fixing. In the background, the Skyworks team bring in another load.

Flat-packed wall panels are lifted and stood in place for fixing. In the background, the Skyworks team bring in another load.

5 of 20
Many hands make light work: the team stands the wall panels in place for fixing.

Many hands make light work: the team stands the wall panels in place for fixing.

6 of 20
Maria Hosking from SGA and Col Strachan fixing the interior plywood lining from Carter Holt Harvey.

Maria Hosking from SGA and Col Strachan fixing the interior plywood lining from Carter Holt Harvey.

7 of 20
Kat Hebden, Terese Fitzgerald, Georgina Gray and Elspeth Gray fixing the pre-cut decking for the internal breezeway at the end of Day 2 of assembly. Garapa decking kindly donated by 				Rosenfeld Kidson.

Kat Hebden, Terese Fitzgerald, Georgina Gray and Elspeth Gray fixing the pre-cut decking for the internal breezeway at the end of Day 2 of assembly. Garapa decking kindly donated by Rosenfeld Kidson.

8 of 20
Krupa Patel and Joanna Jack fixing the Metalcraft corrugate cladding to the subfloor.

Krupa Patel and Joanna Jack fixing the Metalcraft corrugate cladding to the subfloor.

9 of 20
The final lift of day 2 of assembly – the upper wall panel is lifted by helicopter almost seamlessly into place.

The final lift of day 2 of assembly – the upper wall panel is lifted by helicopter almost seamlessly into place.

10 of 20
Metalcraft Thermospan SIP roof panels are lifted by the Skyworks team from the barge deck in the passage below the site.

Metalcraft Thermospan SIP roof panels are lifted by the Skyworks team from the barge deck in the passage below the site.

11 of 20
Progress after day 3 of assembly: the Metalcraft Thermospan SIP roof panels are on, the pitch imitates the natural contour and bush form.

Progress after day 3 of assembly: the Metalcraft Thermospan SIP roof panels are on, the pitch imitates the natural contour and bush form.

12 of 20
Exterior of the finished Motu Kaikoura Community Trust kitchen/dining/living facility.

Exterior of the finished Motu Kaikoura Community Trust kitchen/dining/living facility.

13 of 20
The new building nestles into the bush as if it has always been there.

The new building nestles into the bush as if it has always been there.

14 of 20
Beautiful views from the newly finished Motu Kaikoura building.

Beautiful views from the newly finished Motu Kaikoura building.

15 of 20
Aerial shot of the Motu Kaikoura building.

Aerial shot of the Motu Kaikoura building.

16 of 20
The use of plywood creates a warm and welcoming interior.

The use of plywood creates a warm and welcoming interior.

17 of 20
Bright and airy living area inside the Motu Kaikoura building.

Bright and airy living area inside the Motu Kaikoura building.

18 of 20
Kitchen area of the Motu Kaikoura Community Trust kitchen/dining/living facility.

Kitchen area of the Motu Kaikoura Community Trust kitchen/dining/living facility.

19 of 20
The newly completed building is situated in a beautiful bay on Motu Kaikoura.

The newly completed building is situated in a beautiful bay on Motu Kaikoura.

20 of 20

Maria Hosking from SGA reports on the installation and finishing of the SGA and Architecture+Women•NZ Motu Kaikoura Building Workshop.

The newly completed building is situated in a beautiful bay on Motu Kaikoura.

The kitchen/dining/living facility for the Motu Kaikoura Community Trust is almost complete, and what a life-changing process it has been. The 20-week course, led by Strachan Group Architects’ director Dave Strachan, invited 16 practicing architects and architectural graduates to prefabricate the SGA design in the SGA Workshop in Kingsland for final transport to Kaikoura Island (off Great Barrier Island) in the Hauraki Gulf.

The first weekend of December 2017 was set for the dismantled and rigorously packaged building components to be transported by road, sea and sky to the remote and protected island. We had successfully completed other prefab projects transported by Hiab truck in various modular and/or panelised states, but this was a whole new ball game.

The logistical nightmare of orchestrating the various transport methods and companies, biosecurity checks, tools, materials, fixings and finishes (it’s a long way to go if you are short a screw!), plus food and supplies for the 16 volunteers, four builders, Dave and myself, was challenging to say the least… and of course it would be up to mother nature to make the final call.

Our prayers for good weather were answered and on 30 November 2017 we travelled by chartered boat to the beautiful Kaikoura Island. Tensions were high after a grave Health and Safety induction with Hamish, our pilot from Skyworks – this was to be an intense and possibly dangerous three days of action and we all had a part to play to ensure that it ran smoothly and that no-one’s safety was at risk.

High pressure to unpack the pre-cut deck joists from the flat-packed floor cartridges between helicopter drops.

We arrived, set up camp and got to work straight away preparing the building site, checking the foundations and subfloor installed by local builders, marking heli-drop points, running through the order of events with the team and talking through the many diagrams and spreadsheets that we had prepared to ensure things were clearly communicated and ran to plan. A safe zone was marked out, code words and various roles agreed on. We were ready…

Day 1 – Floors

The floor cartridges (prefinished plywood, LVL framing, insulation and underply) had been packaged in stacks of two to three and coded for transport and assembly. The four builders from Crate Innovation and JR Hosking Carpenters & Co. balanced on the bearers and scaled the scaffolding to receive the 600–900kg packages that came in thick and fast in 6-minute intervals. Pressure was high and in just one hour, the floor cartridges were all in place, screwed together and ready for fixing to the subfloor.

Flat-packed wall panels are lifted and stood in place for fixing. In the background, the Skyworks team bring in another load.

All 17 of us girls ran excitedly under the subfloor to apply the many ‘z’ nails and nail on plates – the sound of that many hammers going at once was deafening but exhilarating! That evening we had a drink on the complete floor and admired the elevation and view. Day 1 was a success – tomorrow we would receive and stand the walls.

Day 2 – Walls

It was Saturday morning and we were in for another beautiful calm and sunny day. Dave was brought over by the heli crew after overseeing the transport of the remainder of the building from SGA Workshop to Wynard Quarter the evening before. We saw the chartered vessel arrive in the sheltered passage out from the site that was formed between Kaikoura Island and Great Barrier Island.

Maria Hosking from SGA and Col Strachan fixing the interior plywood lining from Carter Holt Harvey.

A couple of us shot across by speed boat to check the 17 packages and run through the plan with the Skyworks ground crew on the barge deck. After sorting a couple of hiccups, we were ready to begin. The completed floor platform made it safer to receive the flat-packed prefabricated wall panels (LVL framing, insulation, RAB, Metalcraft corrugate cladding with windows and glazing installed(!)), however we would need to unwrap, stand and fix wall panels between drops, which we knew from the day before unfolded very quickly.

Intermediate drops of interior linings, cabinetry, roof panels, decking etc. were dropped off in specific locations around the site to buy us time standing panels. Pressure was high and when the last wind beam piece was lifted into place by helicopter we all cheered with relief and satisfaction – we had pulled it off! We had done what some thought was impossible for our unique team.

Day 3 – Roof

While the builders manhandled the 70kg Thermospan SIP (Structurally Insulated Panel) roof panels on to the site, the rest of us carried on with fixings, sealants, undercladding, laying decking, sorting materials and installing the overwall cedar sliders.

Beautiful views from the newly finished Motu Kaikoura building.

By that evening we had the roof on and boy did we celebrate, with more delicious cooking from the tightly rostered meal plan, whisky and Dave on the guitar.

The building was left weather tight and locked up over the summer break. Following the pre-line inspection, those from the team that could make it (plus our plumber Tim of Flux Limited and electrician Lloyd of R.C. Gregory) returned to complete the interior lining, cabinetry, services, decks and pergola. The week was, once again, not for the faint hearted! But the weather was great, the sea refreshing and the company outstanding.

The whole project has been invaluable beyond measure for all of us and we often discuss how it’s hard to communicate to others just how significant the experience has been. Although incredibly challenging in more ways than one, we all feel very proud of each other and of the building that now nestles into the landscape as though it were always there. The friendships made and skills gained will be ones that will last a lifetime.

Bright and airy living area inside the Motu Kaikoura building.

The project could not have been possible if it weren’t for the sixteen women who gave up their Fridays and weekends for weeks on end to learn new skills and become better architects. Their generosity and dedication has been unstoppable, and their families, employers and clients that have supported them through this process must be thanked too.

To the many sponsors of building materials and course fees, we thank you for your support and for making this exciting project plausible. We hope that the experiences the new building offers will encourage others who have a passion for New Zealand’s natural heritage to visit Motu Kaikoura and become active participants in its restoration.

You can read the first blog post about the workshop here, and the second here.

Pip Newman in the SGA workshop.

The valued sponsors of the SGA and A+W•NZ Motu Kaikoura Building Workshop were: APL, ArchitectureNow, Blum, Bunnings, Carter Holt Harvey, Cutshop, Fires by Design, Franklins, Fortress Fasteners, GIB, Katalog, LightPlan, Metalcraft, Metro Glass, Nicks Joinery, NZ Steel, Plytech, Prime Panels, Proclima, PSP, Resene, Rinnai, Rosenfield Kidson, Sika and Spax.

ArchitectureNow sponsored Pip Newman, a tutor at Unitec, and would like to congratulate her personally and the rest of the team for the incredible job they’ve done with the Motu Kaikoura project. 


More review